14 sections with “time extensions”

  • FAR 52.211-13 Time Extensions.
    As prescribed in 11.503(c), insert the following clause: Time Extensions (SEP 2000) Time extensions for contract changes will depend upon the extent, if any, by which the changes cause delay in the completion of the various elements of co…
  • FAR 52.243-7 Notification of Changes.
    …s affected by the alleged change are estimated; and (6) The Contractor's estimate of the time by which the Government must respond to the Contractor's notice to minimize cost, delay or disruption of performance. (c) Continued performance.…
  • FAR 33.104 Protests to GAO.
    …l be made available to non-intervening actual or prospective offerors within a reasonable time after submittal of an agency report to the GAO. The protest file shall include an index and as appropriate— (A) The protest; (B) The offer subm…
  • FAR 42.302 Contract administration functions.
    …ribed in agency acquisition regulations. (15) Manage special bank accounts. (16) Ensure timely notification by the contractor of any anticipated overrun or underrun of the estimated cost under cost-reimbursement contracts. (17) Monitor t…
  • FAR 52.216-7 Allowable Cost and Payment.
    …plan contributions), the term costs includes only— (i) Those recorded costs that, at the time of the request for reimbursement, the Contractor has paid by cash, check, or other form of actual payment for items or services purchased directl…
  • FAR 52.227-11 Patent Rights—Ownership by the Contractor.
    …overnment obtains title, unless the Contractor fails to disclose the invention within the times specified in paragraph (c) of this clause. The Contractor's license extends to any domestic subsidiaries and affiliates within the corporate str…
  • DFARS 252.227-7038 Patent Rights—Ownership by the Contractor (Large Business).
    …overnment obtains title, unless the Contractor fails to disclose the invention within the times specified in paragraph (c) of this clause. The Contractor's license- (A) Extends to any domestic subsidiaries and affiliates within the corpora…
  • FAR 9.406-3 Procedures.
    …period for good cause. The official record closes upon the expiration of the contractor's time to submit information and argument in opposition, including any extensions (see paragraph (b)(1) of this section). (2)(i) In actions in which ad…
  • FAR 11.503 Contract clauses.
    …s for delay of each separate part or stage of the work. (c) Use the clause at 52.211-13, Time Extensions, in solicitations and contracts for construction that use the clause at 52.211-12, Liquidated Damages—Construction, when that clause h…
  • FAR 17.204 Contracts.
    … be exercised. (c) The period shall be set so as to provide the contractor adequate lead time to ensure continuous production. (d) The period may extend beyond the contract completion date for service contracts. This is necessary for situ…
  • FAR 52.217-2 Cancellation Under Multiyear Contracts.
    …ch notice of cancellation is provided. Cancellation shall occur by the date or within the time period specified in the Schedule, unless a later date is agreed to, if the Contracting Officer (1) notifies the Contractor that funds are not ava…
  • FAR 8.705-4 Compliance with orders.
    (a) The central nonprofit agency shall inform the ordering office of changes in lead time experienced by its AbilityOne participating nonprofit agencies to minimize requests for extensions once the ordering office places an order. (b) The …
  • FAR 42.705-1 Contracting officer determination procedure.
    …considered as resident if at least 75 percent of the administrative contracting officer's time is devoted to a single contractor. (3) For business units not included in paragraph (a)(1) or (a)(2) of this subsection, the contracting officer…
  • FAR 52.207-5 Option To Purchase Equipment.
    …tive date of the purchase will be specified in the unilateral modification and may be any time during the period of the contract, including any extensions thereto. (b) Except for final payment and transfer of title to the Government, the l…

FAR (chapter 1)

DFARS (chapter 2, Defense)

Source: eCFR, 48 CFR chapters 1 and 2 (GPO GovInfo bulk data) ↗. Rule changes in progress: FAR, DFARS. Terms: glossary.