48 CFR · Federal Acquisition Regulation and Defense supplement

FAR and DFARS navigator

The codified text (eCFR, as of 2026-10-02). Under the Revolutionary FAR Overhaul ↗, agencies follow class deviations with new text for many parts while the formal rules go through the Federal Register: check the solicitation and your contract's clauses, which rule.

Ask the FAR

Try: · · ·

Clear

13 sections with “Alternative payment protection”

  • FAR 52.228-13 Alternative Payment Protections.
    As prescribed in 28.102-3(b), insert the following clause: Alternative Payment Protections (JUL 2000) (a) The Contractor shall submit one of the following payment protections: (b) The amount of the payment protection shall be 100 percent…
  • FAR 28.102 Performance and payment bonds and alternative payment protections for construction contracts.
  • DFARS 228.102 Performance and payment bonds and alternative payment protections for construction contracts.
  • FAR 28.102-1 General.
    …ular consideration to inclusion of an irrevocable letter of credit as one of the selected alternatives: (i) A payment bond. (ii) An irrevocable letter of credit (ILC). (iii) A tripartite escrow agreement. The prime contractor establishes…
  • FAR 28.102-2 Amount required.
    …r the protection of the Government, the penal amount of the payment bond or the amount of alternative payment protection must equal— (1) 100 percent of the original contract price; and (2) If the contract price increases, an additional am…
  • FAR 52.228-11 Individual Surety—Pledge of Assets.
    …iod, or for 1 year following final payment, whichever is later. (2) Contracts subject to alternative payment protection (see FAR 28.102-1(b)(1)). For the full contract performance period plus 1 year. (3) Other contracts not subject to the…
  • FAR 2.101 Definitions.
    …ering the foregoing services, outputs may take the form of information, advice, opinions, alternatives, analyses, evaluations, recommendations, training and the day-to-day aid of support personnel needed for the successful performance of on…
  • FAR 28.000 Scope of part.
    …lt from the use of the sealed bid or negotiated methods. It covers bid guarantees, bonds, alternative payment protections, security for bonds, and insurance.
  • FAR 28.100 Scope of subpart.
    This subpart prescribes requirements and procedures for the use of bonds, alternative payment protections, and all types of bid guarantees.
  • FAR 28.102-3 Contract clauses.
    …t set a period of time for return of executed bonds. (b) Insert the clause at 52.228-13, Alternative Payment Protections, in solicitations and contracts for construction, when the estimated or actual value exceeds $35,000 but does not exce…
  • FAR 28.203-3 Release of security interest.
    … payment bond during the 1 year period following final payment. (2) Contracts subject to alternative payment protection. See section 28.102-1, paragraph (b)(1). The security interest shall be maintained for the full contract performance pe…
  • FAR 32.410 Findings, determination, and authorization.
    …g is an example of the format and text of findings, determination, and authorization with alternative words, phrases, and paragraphs to be selected to conform to the circumstances involved: Findings, Determination, and Authorization for Ad…
  • DFARS 228.102-1 General.
    …$150,000, payment protection sufficient to pay labor and material costs, using any of the alternatives listed at FAR 28.102-1(b)(1). (2) For fixed-price construction subcontracts over $150,000— (i) A payment bond sufficient to pay labor a…

FAR (chapter 1)

DFARS (chapter 2, Defense)

Source: eCFR, 48 CFR chapters 1 and 2 (GPO GovInfo bulk data) ↗. Rule changes in progress: FAR, DFARS. Terms: glossary.