  • FAR 32.007 Contract financing payments.
    …ocedures or otherwise specified in paragraph (b) of this section, the due date for making contract financing payments by the designated payment office is the 30th day after the designated billing office receives a proper contract financing …
  • FAR 32.207 Administration and payment of commercial financing payments.
    (a) Responsibility. The contracting officer responsible for administration of the contract shall be responsible for review and approval of contract financing requests. (b) Approval of financing requests. Unless otherwise provided in agency…
  • FAR 32.504 Subcontracts under prime contracts providing progress payments.
    (a) Subcontracts may include either performance-based payments, provided they meet the criteria in 32.1003, or progress payments, provided they meet the criteria in subpart 32.5 for customary progress payments, but not both. Subcontracts fo…
  • FAR 42.302 Contract administration functions.
    (a) The contracting officer normally delegates the following contract administration functions to a CAO. The contracting officer may retain any of these functions, except those in paragraphs (a)(5), (a)(9), (a)(11), and (a)(12) of this sect…
  • FAR 52.212-4 Contract Terms and Conditions—Commercial Products and Commercial Services.
    As prescribed in 12.301(b)(3), insert the following clause: Contract Terms and Conditions—Commercial Products and Commercial Services (NOV 2023) (a) Inspection/Acceptance. The Contractor shall only tender for acceptance those items that c…
  • FAR 52.232-29 Terms for Financing of Purchases of Commercial Products and Commercial Services.
    …for Financing of Purchases of Commercial Products and Commercial Services (NOV 2021) (a) Contractor entitlement to financing payments. The Contractor may request, and the Government shall pay, a contract financing payment as specified else…
  • FAR 53.232 Contract financing (SF 1443).
    SF 1443 (NOV 2021), Contractor's Request for Progress Payment. SF 1443 is prescribed for use in obtaining contractors' requests for progress payments.
  • DFARS 212.301 Solicitation provisions and contract clauses for the acquisition of commercial products and commercial services.
    …7301. (f) The following additional provisions and clauses apply to DoD solicitations and contracts using FAR part 12 procedures for the acquisition of commercial products and commercial services. If the offeror has completed any of the fol…
  • DFARS 252.217-7027 Contract Definitization.
    As prescribed in 217.7406(b), use the following clause: Contract Definitization (MAY 2023) (a) A___ [insert specific type of contract action] is contemplated. The Contractor agrees to begin promptly negotiating with the Contracting Office…
  • DFARS 252.232-7003 Electronic Submission of Payment Requests and Receiving Reports.
    …ment Requests and Receiving Reports (DEC 2018) (a) Definitions. As used in this clause— Contract financing payment means an authorized Government disbursement of monies to a contractor prior to acceptance of supplies or services by the Go…
  • DFARS 252.232-7012 Performance-Based Payments—Whole-Contract Basis.
    …escribed in 232.1005-70(a)(1), use the following clause: PERFORMANCE-BASED PAYMENTS—WHOLE-CONTRACT BASIS (DEC 2022) (a) Performance-based payments shall form the basis for the contract financing payments provided under this contract, and s…
  • FAR 32.001 Definitions.
    …ayment that is not a commercial advance payment or a delivery payment. These payments are contract financing payments for prompt payment purposes (i.e., not subject to the interest penalty provisions of the Prompt Payment Act in accordance …
  • FAR 52.232-36 Payment by Third Party.
    …y (MAY 2014) (a) General. (1) Except as provided in paragraph (a)(2) of this clause, the Contractor agrees to accept payments due under this contract, through payment by a third party in lieu of payment directly from the Government, in acc…
  • FAR 2.101 Definitions.
    … or term when used in that part, subpart, or section. Acquisition means the acquiring by contract with appropriated funds of supplies or services (including construction) by and for the use of the Federal Government through purchase or lea…
  • FAR 10.002 Procedures.
    … on such factors as urgency, estimated dollar value, complexity, and past experience. The contracting officer may use market research conducted within 18 months before the award of any task or delivery order if the information is still curr…
  • FAR 31.205-41 Taxes.
    … above, but upon which a claim of illegality or erroneous assessment exists; provided the contractor, before paying such taxes— (i) Promptly requests instructions from the contracting officer concerning such taxes; and (ii) Takes all acti…
  • FAR 32.106 Order of preference.
    The contracting officer must consider the following order of preference when a contractor requests contract financing, unless an exception would be in the Government's best interest in a specific case: (a) Private financing without Governm…
  • FAR 32.304-2 Certificate of eligibility.
    (a) The contracting officer shall prepare the certificate of eligibility for a contract that the contracting officer deems to be of material consequence, when— (1) The contract financing office requests it; (2) Another interested agency r…
  • FAR 32.1004 Procedures.
    Performance-based payments may be made either on a whole contract or on a deliverable item basis, unless otherwise prescribed by agency regulations. Financing payments to be made on a whole contract basis are applicable to the entire contra…
  • FAR 32.1007 Administration and payment of performance-based payments.
    (a) Responsibility. The contracting officer responsible for administering performance-based payments (see 42.302(a)(13)) for the contract shall review and approve all performance-based payments for that contract. (b) Approval of financing …
  • FAR 52.232-16 Progress Payments.
    … clause: Progress Payments (NOV 2021) The Government will make progress payments to the Contractor when requested as work progresses, but not more frequently than monthly, in amounts of $2,500 or more approved by the Contracting Officer, …
  • FAR 52.232-30 Installment Payments for Commercial Products and Commercial Services.
    …se: Installment Payments for Commercial Products and Commercial Services (NOV 2021) (a) Contractor entitlement to financing payments. The Contractor may request, and the Government shall pay, a contract financing installment payment as sp…
  • FAR 52.232-32 Performance-Based Payments.
    …ns on payments. Subject to such other limitations and conditions as are specified in this contract and this clause, the amount of payments and limitations on payments shall be specified in the contract's description of the basis for payment…
  • DFARS 201.402 Policy.
    (1) The Principal Director, Defense Pricing, Contracting, and Acquisition Policy, Office of the Under Secretary of Defense (Acquisition and Sustainment) (OUSD(A&S)DPCAP), is the approval authority within DoD for any individual or class devi…
  • DFARS 217.7404-3 Definitization schedule.
    …at provide for definitization by the earlier of— (1) The date that is 180 days after the contractor submits a qualifying proposal. This date may not be extended beyond an additional 90 days without a written determination by the head of th…
  • DFARS 252.232-7002 Progress Payments for Foreign Military Sales Acquisitions.
    …ng clause: Progress Payments for Foreign Military Sales Acquisitions (MAY 2023) If this contract includes foreign military sales (FMS) requirements, the Contractor shall— (a) Submit separate progress payment requests for the FMS and U.S.…
  • DFARS 252.232-7006 Wide Area WorkFlow Payment Instructions.
    …bmission of Payment Requests and Receiving Reports. (c) WAWF access. To access WAWF, the Contractor shall— (1) Have a designated electronic business point of contact in the System for Award Management at https://www.sam.gov and (2) Be re…
  • DFARS 252.232-7013 Performance-Based Payments—Deliverable-Item Basis.
    …erable-Item Basis (DEC 2022) (a) Performance-based payments shall form the basis for the contract financing payments provided under this contract and shall apply to Contract Line Item Number(s) (CLIN(s)) [Contracting Officer insert applica…
  • DFARS 252.232-7018 Progress Payments—Multiple Lots.
    … single progress payment rate is used. Multiple lots means more than one lot on a single contract where progress payment proration is performed on a lot-wide, versus contract-wide, basis. (b) When submitting progress payment requests unde…

FAR (chapter 1)

DFARS (chapter 2, Defense)

Source: eCFR, 48 CFR chapters 1 and 2 (GPO GovInfo bulk data) ↗. Rule changes in progress: FAR, DFARS. Terms: glossary.