22 sections with “cost-plus-fixed-fee contract”
- FAR 16.306 Cost-plus-fixed-fee contracts.(a) Description. A cost-plus-fixed-fee contract is a cost-reimbursement contract that provides for payment to the contractor of a negotiated fee that is fixed at the inception of the contract. The fixed fee does not vary with actual cost, b…
- DFARS 216.306 Cost-plus-fixed-fee contracts.…ii) of this section, annual military construction appropriations acts prohibit the use of cost-plus-fixed-fee contracts that— (A) Are funded by a military construction appropriations act; (B) Are estimated to exceed $25,000; and (C) Will…
- DFARS 236.271 Cost-plus-fixed-fee contracts.Annual military construction appropriations acts restrict the use of cost-plus-fixed-fee contracts (see 216.306(c)). See also 216.301-3 regarding the prohibition on the use of certain cost-reimbursement contracts in connection with a milita…
- FAR 16.307 Contract clauses.…cer shall insert the clause at 52.216-8, Fixed Fee, in solicitations and contracts when a cost-plus-fixed-fee contract (other than a construction contract) is contemplated. (c) The contracting officer shall insert the clause at 52.216-9, F…
- DFARS 216.405-2 Cost-plus-award-fee contracts.… (i) The cost-plus-award-fee contract shall not be used— (A) To avoid— (1) Establishing cost-plus-fixed-fee contracts when the criteria for cost-plus-fixed-fee contracts apply; or (2) Developing objective targets so a cost-plus-incentive…
- FAR 15.404-4 Profit.…41 U.S.C. 3905): (A) For experimental, developmental, or research work performed under a cost-plus-fixed-fee contract, the fee shall not exceed 15 percent of the contract's estimated cost, excluding fee. (B) For architect-engineer service…
- FAR 52.219-10 Incentive Subcontracting Program.…e unilateral decisions made solely at the discretion of the Government. (c) If this is a cost-plus-fixed-fee contract, the sum of the fixed fee and the incentive fee earned under this contract may not exceed the limitations in 15.404-4 of …
- DFARS 211.503 Contract clauses.…Liquidated Damages—Construction, in all construction contracts exceeding $900,000, except cost-plus-fixed-fee contracts or contracts where the contractor cannot control the pace of the work. Use of the clause in contracts of $900,000 or les…
- DFARS 215.404-71-3 Contract type risk and working capital adjustment.… not receive the working capital adjustment. (5) These types of contracts are considered cost-plus-fixed-fee contracts for the purposes of assigning profit values. They shall not receive the working capital adjustment in Block 25. However,…
- DFARS 216.601 Time-and-materials contracts.…e work or to anticipate costs with any reasonable degree of certainty; (3) Address why a cost-plus-fixed-fee term or other cost-reimbursement, incentive, or fixed-price contract or order is not appropriate; for contracts (including indefin…
- FAR 11.503 Contract clauses.…uidated Damages—Construction, in solicitations and contracts for construction, other than cost-plus-fixed-fee, when the contracting officer determines that liquidated damages are appropriate (see 11.501(a)). If the contract specifies more t…
- FAR 36.208 Concurrent performance of firm-fixed-price and other types of construction contracts.In view of potential labor and administrative problems, cost-plus-fixed-fee, price-incentive, or other types of contracts with cost variation or cost adjustment features shall not be permitted concurrently, at the same work site, with firm-…
- FAR 52.244-2 Subcontracts.…eless shall notify the Contracting Officer reasonably in advance of entering into any (i) cost-plus-fixed-fee subcontract, or (ii) fixed-price subcontract that exceeds either the simplified acquisition threshold, as defined in FAR 2.101 on …
- FAR 52.203-10 Price or Fee Adjustment for Illegal or Improper Activity.…The price or fee reduction referred to in paragraph (a) of this clause shall be— (1) For cost-plus-fixed-fee contracts, the amount of the fee specified in the contract at the time of award; (2) For cost-plus-incentive-fee conrtracts, the …
- FAR 52.216-8 Fixed Fee.…rescribed in 16.307(b), insert the following clause in solicitations and contracts when a cost-plus-fixed-fee contract (other than a facilities contract or a construction contract) is contemplated. Fixed Fee (JUN 2011) (a) The Government …
- DFARS 232.703-70 Military construction appropriations act restriction.…appropriations acts restrict the use of funds appropriated by the acts for payments under cost-plus-fixed-fee contracts (see 216.306(c)).
- FAR 44.201-2 Advance notification requirements.…proved purchasing system, 10 U.S.C. 3322(c) requires notification before the award of any cost-plus-fixed-fee subcontract, or any fixed-price subcontract that exceeds the greater of the simplified acquisition threshold or 5 percent of the t…
- DFARS 252.246-7001 Warranty of data.…firm-fixed-price subcontract; (B) Seventy-five percent of the total subcontract fee in a cost-plus-fixed-fee or cost-plus-award-fee subcontract; or (C) Seventy-five percent of the total subcontract target profit or fee in a fixed-price-in…
- FAR 16.101 General.…ctor has full responsibility for the performance costs and resulting profit (or loss), to cost-plus-fixed-fee, in which the contractor has minimal responsibility for the performance costs and the negotiated fee (profit) is fixed. In between…
- FAR 52.216-9 Fixed Fee—Construction.…rescribed in 16.307(c), insert the following clause in solicitations and contracts when a cost-plus-fixed-fee construction contract is contemplated: Fixed Fee—Construction (JUN 2011) (a) The Government shall pay to the Contractor for perf…
- DFARS 215.404-72 Modified weighted guidelines method for nonprofit organizations other than FFRDCs.… Secretary of Defense or a Secretary of a Department as receiving sustaining support on a cost-plus-fixed-fee basis from a particular DoD department or agency, compute a fee objective for covered actions using the weighted guidelines method…
- DFARS 216.301-3 Limitations.…truction project or a military family housing project, contracting officers shall not use cost-plus-fixed-fee, cost-plus-award-fee, or cost-plus-incentive-fee contract types (10 U.S.C. 3323). This applies notwithstanding a declaration of wa…
FAR (chapter 1)
- Part 1 Federal Acquisition Regulations System 58 sections
- Part 2 Definitions of Words and Terms 3 sections
- Part 3 Improper Business Practices and Personal Conflicts of Interest 98 sections
- Part 4 Administrative and Information Matters 116 sections
- Part 5 Publicizing Contract Actions 34 sections
- Part 6 Competition Requirements 34 sections
- Part 7 Acquisition Planning 34 sections
- Part 8 Required Sources of Supplies and Services 67 sections
- Part 9 Contractor Qualifications 106 sections
- Part 10 Market Research 4 sections
- Part 11 Describing Agency Needs 33 sections
- Part 12 Acquisition of Commercial Products and Commercial Services 38 sections
- Part 13 Simplified Acquisition Procedures 49 sections
- Part 14 Sealed Bidding 82 sections
- Part 15 Contracting by Negotiation 81 sections
- Part 16 Types of Contracts 74 sections
- Part 17 Special Contracting Methods 50 sections
- Part 18 Emergency Acquisitions 34 sections
- Part 19 Small Business Programs 126 sections
- Part 22 Application of Labor Laws to Government Acquisitions 205 sections
- Part 23 Environment, Sustainable Acquisition, and Material Safety 38 sections
- Part 24 Protection of Privacy and Freedom of Information 10 sections
- Part 25 Foreign Acquisition 81 sections
- Part 26 Other Socioeconomic Programs 36 sections
- Part 27 Patents, Data, and Copyrights 59 sections
- Part 28 Bonds and Insurance 61 sections
- Part 29 Taxes 23 sections
- Part 30 Cost Accounting Standards Administration 30 sections
- Part 31 Contract Cost Principles and Procedures 87 sections
- Part 32 Contract Financing 175 sections
- Part 33 Protests, Disputes, and Appeals 23 sections
- Part 34 Major System Acquisition 20 sections
- Part 35 Research and Development Contracting 25 sections
- Part 36 Construction and Architect-engineer Contracts 81 sections
- Part 37 Service Contracting 46 sections
- Part 38 Federal Supply Schedule Contracting 3 sections
- Part 39 Acquisition of Information Technology 14 sections
- Part 40 Information Security and Supply Chain Security 12 sections
- Part 41 Acquisition of Utility Services 17 sections
- Part 42 Contract Administration and Audit Services 84 sections
- Part 43 Contract Modifications 14 sections
- Part 44 Subcontracting Policies and Procedures 24 sections
- Part 45 Government Property 33 sections
- Part 46 Quality Assurance 60 sections
- Part 47 Transportation 106 sections
- Part 48 Value Engineering 13 sections
- Part 49 Termination of Contracts 108 sections
- Part 50 Extraordinary Contractual Actions and the Safety Act 34 sections
- Part 51 Use of Government Sources by Contractors 15 sections
- Part 52 Solicitation Provisions and Contract Clauses 680 sections
- Part 53 Forms 61 sections
DFARS (chapter 2, Defense)
- Part 201 Federal Acquisition Regulations System 24 sections
- Part 202 Definitions of Words and Terms 1 sections
- Part 203 Improper Business Practices and Personal Conflicts of Interest 28 sections
- Part 204 Administrative and Information Matters 76 sections
- Part 205 Publicizing Contract Actions 11 sections
- Part 206 Competition Requirements 20 sections
- Part 207 Acquisition Planning 22 sections
- Part 208 Required Sources of Supplies and Services 31 sections
- Part 209 Contractor Qualifications 55 sections
- Part 210 Market Research 2 sections
- Part 211 Describing Agency Needs 22 sections
- Part 212 Acquisition of Commercial Products and Commercial Services 24 sections
- Part 213 Simplified Acquisition Procedures 23 sections
- Part 214 Sealed Bidding 14 sections
- Part 215 Contracting by Negotiation 66 sections
- Part 216 Types of Contracts 36 sections
- Part 217 Special Contracting Methods 64 sections
- Part 218 Emergency Acquisitions 7 sections
- Part 219 Small Business Programs 47 sections
- Part 222 Application of Labor Laws to Government Acquisitions 56 sections
- Part 223 Environment, Sustainable Acquisition, and Material Safety 34 sections
- Part 224 Protection of Privacy and Freedom of Information 2 sections
- Part 225 Foreign Acquisition 251 sections
- Part 226 Other Socioeconomic Programs 14 sections
- Part 227 Patents, Data, and Copyrights 99 sections
- Part 228 Bonds and Insurance 17 sections
- Part 229 Taxes 9 sections
- Part 230 Cost Accounting Standards Administration 2 sections
- Part 231 Contract Cost Principles and Procedures 13 sections
- Part 232 Contract Financing 74 sections
- Part 233 Protests, Disputes, and Appeals 8 sections
- Part 234 Major System Acquisition 13 sections
- Part 235 Research and Development Contracting 16 sections
- Part 236 Construction and Architect-engineer Contracts 25 sections
- Part 237 Service Contracting 67 sections
- Part 239 Acquisition of Information Technology 38 sections
- Part 241 Acquisition of Utility Services 8 sections
- Part 242 Contract Administration and Audit Services 40 sections
- Part 243 Contract Modifications 18 sections
- Part 244 Subcontracting Policies and Procedures 13 sections
- Part 245 Government Property 23 sections
- Part 246 Quality Assurance 39 sections
- Part 247 Transportation 27 sections
- Part 249 Termination of Contracts 14 sections
- Part 250 Extraordinary Contractual Actions and the Safety Act 16 sections
- Part 251 Use of Government Sources by Contractors 5 sections
- Part 252 Solicitation Provisions and Contract Clauses 405 sections
- Part 253 Forms 10 sections
- Part 270 Defense Contracting Programs 7 sections
Source: eCFR, 48 CFR chapters 1 and 2 (GPO GovInfo bulk data) ↗. Rule changes in progress: FAR, DFARS. Terms: glossary.