196 sections with “final cost”: the first 40

  • FAR 52.242-4 Certification of Final Indirect Costs.
    As prescribed in 42.703-2(f), insert the following clause: Certification of Final Indirect Costs (JAN 1997) (a) The Contractor shall— (1) Certify any proposal to establish or modify final indirect cost rates; (2) Use the format in parag…
  • FAR 31.202 Direct costs.
    (a) No final cost objective shall have allocated to it as a direct cost any cost, if other costs incurred for the same purpose in like circumstances have been included in any indirect cost pool to be allocated to that or any other final cos…
  • FAR 31.203 Indirect costs.
    …r work, indirect costs are those remaining to be allocated to intermediate or two or more final cost objectives. No final cost objective shall have allocated to it as an indirect cost any cost, if other costs incurred for the same purpose, …
  • FAR 42.705 Final indirect cost rates.
    (a) Final indirect cost rates shall be established on the basis of— (1) Contracting officer determination procedure (see 42.705-1) or (2) Auditor determination procedure (see 42.705-2). (b) Within 120 days (or longer period, if approved …
  • FAR 42.703-2 Certificate of indirect costs.
    …U.S.C. 4307, a proposal shall not be accepted and no agreement shall be made to establish final indirect cost rates unless the costs have been certified by the contractor. (b) Waiver of certification. (1) The agency head, or designee, may …
  • FAR 52.216-7 Allowable Cost and Payment.
    …interest penalty provisions of the Prompt Payment Act. Interim payments made prior to the final payment under the contract are contract financing payments, except interim payments if this contract contains Alternate I to the clause at 52.23…
  • FAR 52.230-6 Administration of Cost Accounting Standards.
    …part 16.4); (3) Orders issued under indefinite-delivery contracts and subcontracts where final payment is not based on actual costs incurred (FAR Subpart 16.5); and (4) The fixed-hourly rate portion of time-and-materials and labor-hours c…
  • FAR 52.242-3 Penalties for Unallowable Costs.
    … Costs (DEC 2022) (a) Definition. Proposal, as used in this clause, means either— (1) A final indirect cost rate proposal submitted by the Contractor after the expiration of its fiscal year which— (i) Relates to any payment made on the b…
  • FAR 52.249-6 Termination (Cost-Reimbursement).
    …e reimbursable in whole or in part, under this contract; approval or ratification will be final for purposes of this clause. (6) Transfer title (if not already transferred) and, as directed by the Contracting Officer, deliver to the Govern…
  • FAR 2.101 Definitions.
    …e Federal agency that, on behalf of all Federal agencies, is responsible for establishing final indirect cost rates and forward pricing rates, if applicable, and administering cost accounting standards for all contracts in a business unit. …
  • FAR 16.403-1 Fixed-price incentive (firm target) contracts.
    …er contract clauses. When the contractor completes performance, the parties negotiate the final cost, and the final price is established by applying the formula. When the final cost is less than the target cost, application of the formula r…
  • FAR 16.403-2 Fixed-price incentive (successive targets) contracts.
    …r a lesser degree of contractor cost responsibility than would a formula for establishing final profit and price.) (iv) The production point at which the firm target cost and firm target profit will be negotiated (usually before delivery o…
  • FAR 30.606 Resolving cost impacts.
    …; and (B) Adjust interim payment requests (public vouchers and/or progress payments) and final vouchers to reflect the difference between the costs paid using the noncompliant practice and the costs that should have been paid using the com…
  • FAR 42.707 Cost-sharing rates and limitations on indirect cost rates.
    …pment contracts, see 35.003(b). (b)(1) Other situations may make it prudent to provide a final indirect cost rate ceiling in a contract. Examples of such circumstances are when the proposed contractor— (i) Is a new or recently reorganized…
  • FAR 49.303-4 Adjustment of indirect costs.
    …able Cost and Payment, and it appears that adjustment of indirect costs will unduly delay final settlement, the TCO, after obtaining information from the appropriate audit agency, may agree with the contractor to— (1) Negotiate the amount …
  • FAR 52.216-15 Predetermined Indirect Cost Rates.
    … upon by the parties, as specified below. (b)(1) The Contractor shall submit an adequate final indirect cost rate proposal to the Contracting Officer (or cognizant Federal agency official) and auditor within the 6-month period following th…
  • FAR 52.216-16 Incentive Price Revision—Firm Target.
    …price revision in accordance with this clause; provided, that in no event shall the total final price of these items exceed the ceiling price of ___ dollars ($___). Any supplies or services that are to be (1) ordered separately under, or ot…
  • FAR 52.216-17 Incentive Price Revision—Successive Targets.
    …price revision in accordance with this clause; provided, that in no event shall the total final price of these items exceed the ceiling price of ___ dollars ($___). The prices of these items shown in the Schedule are the initial target pric…
  • DFARS 216.405-2 Cost-plus-award-fee contracts.
    …iate fee distribution to ensure at least 40 percent of the award fee is available for the final evaluation so that the award fee is appropriately distributed over all evaluation periods to incentivize the contractor throughout performance o…
  • DFARS 252.215-7002 Cost Estimating System Requirements.
    …Contractor's response and notify the Contractor, in writing, of the Contracting Officer's final determination concerning— (i) Remaining material weaknesses; (ii) The adequacy of any proposed or completed corrective action; and (iii) Syst…
  • DFARS 252.242-7006 Accounting System Administration.
    …nsistent method for the accumulation and allocation of indirect costs to intermediate and final cost objectives; (5) Accumulation of costs under general ledger control; (6) Reconciliation of subsidiary cost ledgers and cost objectives to …
  • FAR 15.403-4 Requiring certified cost or pricing data (10 U.S.C. chapter 271 and 41 U.S.C. chapter 35).
    …required are included for administrative convenience in the same modification. Negotiated final pricing actions (such as termination settlements and total final price agreements for fixed-price incentive and redeterminable contracts) are co…
  • FAR 15.407-1 Defective certified cost or pricing data.
    …t or pricing data are found to be inaccurate, incomplete, or noncurrent as of the date of final agreement on price or an earlier date agreed upon by the parties given on the contractor's or subcontractor's Certificate of Current Cost or Pri…
  • FAR 31.205-18 Independent research and development and bid and proposal costs.
    …2) are not applicable, the following apply: (i) IR&D and B&P costs shall be allocated to final cost objectives on the same basis of allocation used for the G&A expense grouping of the profit center (see 31.001) in which the costs are incur…
  • DFARS 225.7303-2 Cost of doing business with a foreign government or an international organization.
    … and (2) Use actual expenditures, to the extent that they are reasonable, in determining final cost. (d) Under paragraph (e)(1)(A) of Section 21 of the Arms Export Control Act (22 U.S.C. 2761), the United States must charge for administra…
  • DFARS 242.705 Final indirect cost rates.
  • FAR 4.804-5 Procedures for closing out contract files.
    …t procedures must ensure that— (1) Disposition of classified material is completed; (2) Final patent report is cleared. If a final patent report is required, the contracting officer may proceed with contract closeout in accordance with th…
  • FAR 15.408 Solicitation provisions and contract clauses.
    … the agreement, include a copy, and describe its nature. H. As soon as practicable after final agreement on price or an earlier date agreed to by the parties, but before the award resulting from the proposal, you must, under the conditions…
  • FAR 30.604 Processing changes to disclosed or established cost accounting practices.
    …r closed) or the fiscal year(s) in which the costs are incurred (i.e., whether or not the final indirect rates have been established); (2) Combine the cost impact for all affected CAS-covered contracts and subcontracts for all segments if …
  • FAR 31.001 Definitions.
    …icable law, regulation, or contract, is specifically named and stated to be unallowable. Final cost objective means (except for subparts 31.3 and 31.6) a cost objective that has allocated to it both direct and indirect costs and, in the co…
  • FAR 31.110 Indirect cost rate certification and penalties on unallowable costs.
    (a) Certain contracts require certification of the indirect cost rates proposed for final payment purposes. See 42.703-2 for administrative procedures regarding the certification provisions and the related contract clause prescription. (b)…
  • FAR 32.904 Determining payment due dates.
    …h day after Government acceptance of supplies delivered or services performed. (A) For a final invoice, when the payment amount is subject to contract settlement actions, acceptance is deemed to occur on the effective date of the contract …
  • FAR 42.703-1 Policy.
    (a) A single agency (see 42.705-1) shall be responsible for establishing final indirect cost rates for each business unit. These rates shall be binding on all agencies and their contracting offices, unless otherwise specifically prohibited …
  • FAR 42.705-1 Contracting officer determination procedure.
    …ntracting officer (or cognizant Federal agency official) responsible for establishing the final indirect cost rates: (1) Business units of a multidivisional corporation under the cognizance of a corporate administrative contracting officer…
  • FAR 42.705-3 Educational institutions.
    (a) General. (1) Postdetermined final indirect cost rates shall be used in the settlement of indirect costs for all cost-reimbursement contracts with educational institutions, unless predetermined final indirect cost rates are authorized an…
  • FAR 42.801 Notice of intent to disallow costs.
    … issued without coordination with the contracting officer or auditor having authority for final indirect cost settlement (see 42.705). (f) In the event the contractor submits a response that disagrees with the notice (see paragraph (b) abo…
  • FAR 42.1503 Procedures.
    …individuals responsible for preparing and reviewing interim evaluations, if prepared, and final evaluations (e.g., contracting officers, contracting officer representatives, project managers, and program managers). Those individuals identif…
  • FAR 52.212-3 Offeror Representations and Certifications—Commercial Products and Commercial Services.
    … considered delinquent if both of the following criteria apply: (A) The tax liability is finally determined. The liability is finally determined if it has been assessed. A liability is not finally determined if there is a pending administr…
  • FAR 52.212-4 Contract Terms and Conditions—Commercial Products and Commercial Services.
    …rence. The Contractor shall proceed diligently with performance of this contract, pending final resolution of any dispute arising under the contract. (e) Definitions. The clause at FAR 52.202-1, Definitions, is incorporated herein by refer…
  • FAR 52.215-2 Audit and Records—Negotiation.
    …(d), and (e) of this clause, for examination, audit, or reproduction, until 3 years after final payment under this contract or for any shorter period specified in Subpart 4.7, Contractor Records Retention, of the Federal Acquisition Regulat…

FAR (chapter 1)

DFARS (chapter 2, Defense)

Source: eCFR, 48 CFR chapters 1 and 2 (GPO GovInfo bulk data) ↗. Rule changes in progress: FAR, DFARS. Terms: glossary.