48 CFR · Federal Acquisition Regulation and Defense supplement
FAR and DFARS navigator
The codified text (eCFR, as of 2026-10-02). Under the Revolutionary FAR Overhaul ↗, agencies follow class deviations with new text for many parts while the formal rules go through the Federal Register: check the solicitation and your contract's clauses, which rule.
Ask the FAR
Try: · · ·
23 sections with “target profit”
- FAR 16.403-1 Fixed-price incentive (firm target) contracts.(a) Description. A fixed-price incentive (firm target) contract specifies a target cost, a target profit, a price ceiling (but not a profit ceiling or floor), and a profit adjustment formula. These elements are all negotiated at the outset.…
- FAR 16.403-2 Fixed-price incentive (successive targets) contracts.(a) Description. (1) A fixed-price incentive (successive targets) contract specifies the following elements, all of which are negotiated at the outset: (i) An initial target cost. (ii) An initial target profit. (iii) An initial profit ad…
- FAR 52.216-16 Incentive Price Revision—Firm Target.As prescribed in 16.406(a), insert the following clause: Incentive Price Revision—Firm Target (JAN 2022) (a) General. The supplies or services identified in the Schedule as Items ___ [Contracting Officer insert Schedule line item numbers]…
- FAR 52.216-17 Incentive Price Revision—Successive Targets.…rescribed in 16.406(b), insert the following clause: Incentive Price Revision—Successive Targets (JAN 2022) (a) General. The supplies or services identified in the Schedule as Items ___ [Contracting Officer insert line item numbers] are s…
- FAR 16.402-1 Cost incentives.…Except for award-fee contracts (see 16.404 and 16.401 (e)), incentive contracts include a target cost, a target profit or fee, and a profit or fee adjustment formula that (within the constraints of a price ceiling or minimum and maximum fee…
- FAR 52.203-10 Price or Fee Adjustment for Illegal or Improper Activity.…ed in the contract at the time of award; (2) For cost-plus-incentive-fee conrtracts, the target fee specified in the contract at the time of award, notwithstanding any minimum fee or “fee floor” specified in the contract. (3) For cost-plu…
- FAR 16.401 General.…to obtain specific acquisition objectives by— (1) Establishing reasonable and attainable targets that are clearly communicated to the contractor; and (2) Including appropriate incentive arrangements designed to (i) motivate contractor eff…
- FAR 32.503-9 Liquidation rates—alternate method.…be increased or decreased in keeping with the successive changes to the contract price or target profit when— (i) The target profit is changed under a fixed-price incentive contract with successive targets; or (ii) A redetermined price in…
- FAR 52.248-1 Value Engineering.…tant contract items affected. Any negative instant contract savings shall be added to the target cost or to the target price and ceiling price, and the amount shall be offset against concurrent and future contract savings. (4) If the Gover…
- DFARS 252.246-7001 Warranty of data.…tional liability under paragraph (d)(3) of this clause shall not exceed 75 percent of the target profit. (ii) If the breach of the warranty is with respect to the data supplied by an equipment subcontractor, the limit of the Contractor's l…
- FAR 16.403 Fixed-price incentive contracts.…pplication of a formula based on the relationship of total final negotiated cost to total target cost. The final price is subject to a price ceiling, negotiated at the outset. The two forms of fixed-price incentive contracts, firm target an…
- FAR 27.202-5 Solicitation provisions and contract clause.…der the contract. If a fixed-price incentive contract is contemplated, change “price” to “target cost and target profit” wherever it appears in the clause. The clause may be used in cost-reimbursement contracts where agency approval of roya…
- FAR 52.226-1 Utilization of Indian Organizations and Indian-Owned Economic Enterprises.…tive Program to the following: (i) The estimated cost of a cost-type contract. (ii) The target cost of a cost-plus-incentive-fee prime contract. (iii) The target cost and ceiling price of a fixed-price incentive prime contract. (iv) The…
- FAR 16.402-2 Performance incentives.…ed to relate profit or fee to results achieved by the contractor, compared with specified targets. (b) To the maximum extent practicable, positive and negative performance incentives shall be considered in connection with service contracts…
- FAR 31.205-6 Compensation for personal services.…rdedafterJune24.pdf. (iii) Exceptions. An agency head may establish one or more narrowly targeted exceptions for scientists, engineers, or other specialists upon a determination that such exceptions are needed to ensure that the executive …
- FAR 48.104-2 Sharing acquisition savings.…contracts, the contracting officer shall add any negative instant contract savings to the target cost or to the target price and ceiling price and then offset these negative instant contract savings and any Government costs against concurre…
- FAR 52.230-6 Administration of Cost Accounting Standards.… (i) Estimated increased cost accumulations are the basis for increasing contract prices, target prices and cost ceilings; and (ii) Estimated decreased cost accumulations are the basis for decreasing contract prices, target prices and cost…
- DFARS 215.404-71-4 Facilities capital employed.…es capital cost of money, with normal, booked costs, to establish a cost objective or the target cost when structuring an incentive type contract. Do not adjust target costs established at the outset even though actual cost of money rates b…
- DFARS 252.226-7001 Utilization of Indian Organizations, Indian-Owned Economic Enterprises, and Native Hawaiian Small Business Concerns.…ause. (2) The incentive amount that may be requested is 5 percent of the estimated cost, target cost, or fixed price included in the subcontract at the time of award to the Indian organization, Indian-owned economic enterprise, or Native H…
- FAR 16.204 Fixed-price incentive contracts.…ract price by a formula based on the relationship of final negotiated total cost to total target cost. Fixed-price incentive contracts are covered in subpart 16.4, Incentive Contracts. See 16.403 for more complete descriptions, application,…
- DFARS 215.404-71-2 Performance risk.…edule; and (vii) Any other factors that affect the contractor's ability to meet the cost targets (e.g., foreign currency exchange rates and inflation rates). (2) Above normal conditions. (i) The contracting officer may assign a higher tha…
- DFARS 244.305-70 Policy.…proposal; (ii) Considering another type of contract, e.g., a fixed-price incentive (firm target) contract instead of firm-fixed-price; (iii) Using additional cost analysis techniques to determine the reasonableness of the cost elements af…
- DFARS 252.232-7007 Limitation of Government's obligation.…otted, an equitable adjustment will be made in the price or prices (including appropriate target, billing, and ceiling prices where applicable) of the item(s), or in the time of delivery, or both. Failure to agree to any such equitable adju…
FAR (chapter 1)
- Part 1 Federal Acquisition Regulations System 58 sections
- Part 2 Definitions of Words and Terms 3 sections
- Part 3 Improper Business Practices and Personal Conflicts of Interest 98 sections
- Part 4 Administrative and Information Matters 116 sections
- Part 5 Publicizing Contract Actions 34 sections
- Part 6 Competition Requirements 34 sections
- Part 7 Acquisition Planning 34 sections
- Part 8 Required Sources of Supplies and Services 67 sections
- Part 9 Contractor Qualifications 106 sections
- Part 10 Market Research 4 sections
- Part 11 Describing Agency Needs 33 sections
- Part 12 Acquisition of Commercial Products and Commercial Services 38 sections
- Part 13 Simplified Acquisition Procedures 49 sections
- Part 14 Sealed Bidding 82 sections
- Part 15 Contracting by Negotiation 81 sections
- Part 16 Types of Contracts 74 sections
- Part 17 Special Contracting Methods 50 sections
- Part 18 Emergency Acquisitions 34 sections
- Part 19 Small Business Programs 126 sections
- Part 22 Application of Labor Laws to Government Acquisitions 205 sections
- Part 23 Environment, Sustainable Acquisition, and Material Safety 38 sections
- Part 24 Protection of Privacy and Freedom of Information 10 sections
- Part 25 Foreign Acquisition 81 sections
- Part 26 Other Socioeconomic Programs 36 sections
- Part 27 Patents, Data, and Copyrights 59 sections
- Part 28 Bonds and Insurance 61 sections
- Part 29 Taxes 23 sections
- Part 30 Cost Accounting Standards Administration 30 sections
- Part 31 Contract Cost Principles and Procedures 87 sections
- Part 32 Contract Financing 175 sections
- Part 33 Protests, Disputes, and Appeals 23 sections
- Part 34 Major System Acquisition 20 sections
- Part 35 Research and Development Contracting 25 sections
- Part 36 Construction and Architect-engineer Contracts 81 sections
- Part 37 Service Contracting 46 sections
- Part 38 Federal Supply Schedule Contracting 3 sections
- Part 39 Acquisition of Information Technology 14 sections
- Part 40 Information Security and Supply Chain Security 12 sections
- Part 41 Acquisition of Utility Services 17 sections
- Part 42 Contract Administration and Audit Services 84 sections
- Part 43 Contract Modifications 14 sections
- Part 44 Subcontracting Policies and Procedures 24 sections
- Part 45 Government Property 33 sections
- Part 46 Quality Assurance 60 sections
- Part 47 Transportation 106 sections
- Part 48 Value Engineering 13 sections
- Part 49 Termination of Contracts 108 sections
- Part 50 Extraordinary Contractual Actions and the Safety Act 34 sections
- Part 51 Use of Government Sources by Contractors 15 sections
- Part 52 Solicitation Provisions and Contract Clauses 680 sections
- Part 53 Forms 61 sections
DFARS (chapter 2, Defense)
- Part 201 Federal Acquisition Regulations System 24 sections
- Part 202 Definitions of Words and Terms 1 sections
- Part 203 Improper Business Practices and Personal Conflicts of Interest 28 sections
- Part 204 Administrative and Information Matters 76 sections
- Part 205 Publicizing Contract Actions 11 sections
- Part 206 Competition Requirements 20 sections
- Part 207 Acquisition Planning 22 sections
- Part 208 Required Sources of Supplies and Services 31 sections
- Part 209 Contractor Qualifications 55 sections
- Part 210 Market Research 2 sections
- Part 211 Describing Agency Needs 22 sections
- Part 212 Acquisition of Commercial Products and Commercial Services 24 sections
- Part 213 Simplified Acquisition Procedures 23 sections
- Part 214 Sealed Bidding 14 sections
- Part 215 Contracting by Negotiation 66 sections
- Part 216 Types of Contracts 36 sections
- Part 217 Special Contracting Methods 64 sections
- Part 218 Emergency Acquisitions 7 sections
- Part 219 Small Business Programs 47 sections
- Part 222 Application of Labor Laws to Government Acquisitions 56 sections
- Part 223 Environment, Sustainable Acquisition, and Material Safety 34 sections
- Part 224 Protection of Privacy and Freedom of Information 2 sections
- Part 225 Foreign Acquisition 251 sections
- Part 226 Other Socioeconomic Programs 14 sections
- Part 227 Patents, Data, and Copyrights 99 sections
- Part 228 Bonds and Insurance 17 sections
- Part 229 Taxes 9 sections
- Part 230 Cost Accounting Standards Administration 2 sections
- Part 231 Contract Cost Principles and Procedures 13 sections
- Part 232 Contract Financing 74 sections
- Part 233 Protests, Disputes, and Appeals 8 sections
- Part 234 Major System Acquisition 13 sections
- Part 235 Research and Development Contracting 16 sections
- Part 236 Construction and Architect-engineer Contracts 25 sections
- Part 237 Service Contracting 67 sections
- Part 239 Acquisition of Information Technology 38 sections
- Part 241 Acquisition of Utility Services 8 sections
- Part 242 Contract Administration and Audit Services 40 sections
- Part 243 Contract Modifications 18 sections
- Part 244 Subcontracting Policies and Procedures 13 sections
- Part 245 Government Property 23 sections
- Part 246 Quality Assurance 39 sections
- Part 247 Transportation 27 sections
- Part 249 Termination of Contracts 14 sections
- Part 250 Extraordinary Contractual Actions and the Safety Act 16 sections
- Part 251 Use of Government Sources by Contractors 5 sections
- Part 252 Solicitation Provisions and Contract Clauses 405 sections
- Part 253 Forms 10 sections
- Part 270 Defense Contracting Programs 7 sections
Source: eCFR, 48 CFR chapters 1 and 2 (GPO GovInfo bulk data) ↗. Rule changes in progress: FAR, DFARS. Terms: glossary.