48 CFR · Federal Acquisition Regulation and Defense supplement
FAR and DFARS navigator
The codified text (eCFR, as of 2026-10-02). Under the Revolutionary FAR Overhaul ↗, agencies follow class deviations with new text for many parts while the formal rules go through the Federal Register: check the solicitation and your contract's clauses, which rule.
Ask the FAR
Try: · · ·
57 sections with “written justification”: the first 40
- FAR 27.404-5 Unauthorized, omitted, or incorrect markings.… or ignore the markings. (2) Agencies shall not cancel or ignore markings without making written inquiry of the contractor and affording the contractor at least 60 days to provide a written justification substantiating the propriety of the…
- FAR 52.227-14 Rights in Data—General.…ical or professional journals, symposia proceedings, or similar works. The prior, express written permission of the Contracting Officer is required to assert copyright in all other data first produced in the performance of this contract. (…
- DFARS 252.227-7037 Validation of Asserted Restrictions on Technical Data.…the Contractor or subcontractor shall be prepared to furnish to the Contracting Officer a written justification for such asserted restrictions in response to a challenge under paragraph (e) of this clause. (d) Prechallenge request for info…
- FAR 23.104 General procedures.(a) Maximum extent practicable. If the requiring activity submits a written justification addressing the reasons described in 23.103(a)(1), the contracting officer may consider it not practicable to procure sustainable products or services.…
- FAR 6.302-4 International agreement.… between the United States and a foreign government or international organization, or the written directions of a foreign government reimbursing the agency for the cost of the acquisition of the supplies or services for such government. (b…
- FAR 23.109 Solicitation provisions and contract clauses.…, in solicitations and contracts— (1) Unless— (i) The requiring activity has provided a written justification that it is not practicable to procure sustainable products and services (see 23.104(a)); (ii) An exception under 23.105 applies…
- FAR 32.006-4 Procedures.…nts to the contractor. The remedy coordination official shall submit to the agency head a written report setting forth the remedy coordination official's findings that support each recommendation. (b) Upon receiving a recommendation from t…
- FAR 52.242-1 Notice of Intent To Disallow Costs.… of this contract— (1) The Contracting Officer may at any time issue to the Contractor a written notice of intent to disallow specified costs incurred or planned for incurrence under this contract that have been determined not to be allowa…
- DFARS 252.204-7010 Requirement for Contractor To Notify DoD if the Contractor's Activities are Subject to Reporting Under the U.S.-International Atomic Energy Agency Additional Protocol.…Agency Additional Protocol (U.S.-IAEA AP), the Contractor shall— (1) Immediately provide written notification to the following DoD Program Manager: [Contracting Officer to insert Program Manager's name, mailing address, e-mail address, te…
- DFARS 252.227-7019 Validation of Asserted Restrictions—Computer Software.…ernment under this contract and shall be prepared to furnish to the Contracting Officer a written justification for such asserted restrictions in response to a request for information under paragraph (d) of this clause or a challenge under …
- FAR 1.107 Certifications.…er unless— (a) The certification requirement is specifically imposed by statute; or (b) Written justification for such certification is provided to the Administrator for Federal Procurement Policy by the Federal Acquisition Regulatory Cou…
- FAR 6.302-1 Only one responsible source and no other supplies or services will satisfy agency requirements.…e. (d) Limitations. (1) Contracts awarded using this authority shall be supported by the written justifications and approvals described in 6.303 and 6.304. (2) For contracts awarded using this authority, the notices required by 5.201 shal…
- FAR 6.302-2 Unusual and compelling urgency.…t. (c) Limitations. (1) Contracts awarded using this authority shall be supported by the written justifications and approvals described in 6.303 and 6.304. These justifications may be made and approved after contract award when preparation…
- FAR 6.302-3 Industrial mobilization; engineering, developmental, or research capability; or expert services.…ocess. (c) Limitations. Contracts awarded using this authority shall be supported by the written justifications and approvals described in 6.303 and 6.304.
- FAR 6.302-5 Authorized or required by statute.…Federal Government. (2) Contracts awarded using this authority shall be supported by the written justifications and approvals described in 6.303 and 6.304, except for— (i) Contracts awarded under paragraph (a)(2)(ii) or (b)(2) of this sec…
- FAR 6.302-6 National security.…t. (c) Limitations. (1) Contracts awarded using this authority shall be supported by the written justifications and approvals described in 6.303 and 6.304. (2) See 5.202(a)(1) for synopsis requirements. (3) This statutory authority requi…
- FAR 7.105 Contents of written acquisition plans.In order to facilitate attainment of the acquisition objectives, the plan must identify those milestones at which decisions should be made (see paragraph (b)(21) of this section). The plan must address all the technical, business, managemen…
- FAR 9.202 Policy.… the agency or designee shall, before establishing a qualification requirement, prepare a written justification— (i) Stating the necessity for establishing the qualification requirement and specifying why the qualification requirement must…
- FAR 16.505 Ordering.… basis in accordance with paragraph (b)(1)(iii)(B) of this section, unless supported by a written determination that one of the circumstances described at 16.505(b)(2)(i) applies to the order and the requirement is waived on the basis of a …
- FAR 22.805 Procedures.…evaluation cannot be completed by the required date, the contracting officer shall submit written justification for the award to the head of the contracting activity, who, after informing the OFCCP regional office, may then approve the awar…
- FAR 23.105 Exceptions.…s for ozone depleting substances per 23.107-4 (see 23.109(d)) (42 U.S.C. 7671l), unless a written justification exists as described at 23.104(a) (42 U.S.C. 6962(c)(1) and 7 U.S.C. 8102(a)(1)(B)). (c) Energy-consuming products or systems de…
- FAR 27.306 Licensing background patent rights to third parties.…ntractor that are not subject inventions unless the agency head has approved and signed a written justification in accordance with paragraph (b) of this section. The agency head may not delegate this authority and may exercise the authority…
- FAR 31.205-46 Travel costs.…ions referred in paragraph (a)(2)(i), (ii), or (iii) of this section, must exist. (ii) A written justification for use of the higher amounts must be approved by an officer of the contractor's organization or designee to ensure that the aut…
- FAR 49.206-3 Submission of inventory disposal schedules.…ys from the effective date of termination unless otherwise extended by the TCO based on a written justification to support the extension. The inventory schedules shall be prepared on Standard Form 1428, Inventory Disposal Schedule.
- FAR 49.303-2 Submission of inventory disposal schedules.…ys from the effective date of termination unless otherwise extended by the TCO based on a written justification to support the extension. The inventory disposal schedules shall be prepared on Standard Form 1428, Inventory Disposal Schedule.
- DFARS 201.107 Certifications.…RS unless— (1) The certification requirement is specifically imposed by statute; or (2) Written justification for such certification is provided to the Secretary of Defense by the Under Secretary of Defense (Acquisition and Sustainment), …
- DFARS 201.304 Agency control and compliance procedures.…n unless— (i) The certification requirement is specifically imposed by statute; or (ii) Written justification for such certification is provided to the Secretary of Defense by USD(A&S), and the Secretary of Defense approves in writing the…
- DFARS 204.470-2 National security exclusion.…nt to determine if, and by what means, access may be granted to the IAEA; or (2) Provide written justification to the component or agency treaty office for application of the national security exclusion at that location to exclude access b…
- DFARS 226.7202 Policy and procedures.… the contracting officer elects to use this Demonstration Project, FAR 6.302-5 requires a written justification and approval to limit competition to eligible contractors. In the justification, identify the statutory authority for the Demons…
- DFARS 234.004 Acquisition strategy.… contract is selected, the contract file shall include the milestone decision authority's written determination that— (1) The program is so complex and technically challenging that it would not be practicable to reduce program risk to a le…
- FAR 8.405-3 Blanket purchase agreements (BPAs).…le contractors that can fulfill the requirements, the contracting officer shall prepare a written determination explaining that no additional contractors capable of fulfilling the requirements could be identified despite reasonable efforts …
- FAR 8.405-6 Limiting sources.…to provide access through eBuy; or (C) The agency's senior procurement executive makes a written determination that access through e-Buy is not in the Government's interest. (4) When applicable, the documentation and posting requirements …
- FAR 13.106-1 Soliciting competition.…able for contract actions exceeding $25,000 unless covered by an exception in 5.202. (d) Written solicitations. If obtaining electronic or oral quotations is uneconomical or impracticable, the contracting officer should issue paper solicit…
- FAR 19.502-8 Rejecting Small Business Administration recommendations.(a) If the contracting officer rejects a recommendation of the SBA, written notice shall be furnished to the appropriate SBA representative within 5 working days of the contracting officer's receipt of the recommendation. (b) The SBA PCR (…
- FAR 49.109-7 Settlement by determination.…contractor at least 15 days notice by certified mail (return receipt requested) to submit written evidence, so as to reach the TCO on or before a stated date, substantiating the amount previously proposed. (c) Justification of settlement p…
- DFARS 227.7103-13 Government right to review, verify, challenge, and validate asserted restrictions.…section, contracting officers may request the person asserting a restriction to furnish a written explanation of the facts and supporting documentation for the assertion in sufficient detail to enable the contracting officer to ascertain th…
- DFARS 252.244-7001 Contractor Purchasing System Administration.…erstand the weakness or deficiency. (2) The Contractor shall respond within 30 days to a written initial determination from the Contracting Officer that identifies material weaknesses in the Contractor's purchasing system. If the Contracto…
- FAR 4.2305 Waivers.…). If a waiver is being pursued, then the contracting officer may not make an award until written approval is obtained that the waiver has been granted.
- FAR 5.102 Availability of solicitations.…solicitation through the GPE; or (iii) The agency's senior procurement executive makes a written determination that access through the GPE is not in the Government's interest. (6) When an acquisition contains brand name specifications, th…
- FAR 6.302-7 Public interest.…ty may be used when none of the other authorities in 6.302 apply. (c) Limitations. (1) A written determination to use this authority shall be made in accordance with subpart 1.7, by (i) the Secretary of Defense, the Secretary of the Army, …
FAR (chapter 1)
- Part 1 Federal Acquisition Regulations System 58 sections
- Part 2 Definitions of Words and Terms 3 sections
- Part 3 Improper Business Practices and Personal Conflicts of Interest 98 sections
- Part 4 Administrative and Information Matters 116 sections
- Part 5 Publicizing Contract Actions 34 sections
- Part 6 Competition Requirements 34 sections
- Part 7 Acquisition Planning 34 sections
- Part 8 Required Sources of Supplies and Services 67 sections
- Part 9 Contractor Qualifications 106 sections
- Part 10 Market Research 4 sections
- Part 11 Describing Agency Needs 33 sections
- Part 12 Acquisition of Commercial Products and Commercial Services 38 sections
- Part 13 Simplified Acquisition Procedures 49 sections
- Part 14 Sealed Bidding 82 sections
- Part 15 Contracting by Negotiation 81 sections
- Part 16 Types of Contracts 74 sections
- Part 17 Special Contracting Methods 50 sections
- Part 18 Emergency Acquisitions 34 sections
- Part 19 Small Business Programs 126 sections
- Part 22 Application of Labor Laws to Government Acquisitions 205 sections
- Part 23 Environment, Sustainable Acquisition, and Material Safety 38 sections
- Part 24 Protection of Privacy and Freedom of Information 10 sections
- Part 25 Foreign Acquisition 81 sections
- Part 26 Other Socioeconomic Programs 36 sections
- Part 27 Patents, Data, and Copyrights 59 sections
- Part 28 Bonds and Insurance 61 sections
- Part 29 Taxes 23 sections
- Part 30 Cost Accounting Standards Administration 30 sections
- Part 31 Contract Cost Principles and Procedures 87 sections
- Part 32 Contract Financing 175 sections
- Part 33 Protests, Disputes, and Appeals 23 sections
- Part 34 Major System Acquisition 20 sections
- Part 35 Research and Development Contracting 25 sections
- Part 36 Construction and Architect-engineer Contracts 81 sections
- Part 37 Service Contracting 46 sections
- Part 38 Federal Supply Schedule Contracting 3 sections
- Part 39 Acquisition of Information Technology 14 sections
- Part 40 Information Security and Supply Chain Security 12 sections
- Part 41 Acquisition of Utility Services 17 sections
- Part 42 Contract Administration and Audit Services 84 sections
- Part 43 Contract Modifications 14 sections
- Part 44 Subcontracting Policies and Procedures 24 sections
- Part 45 Government Property 33 sections
- Part 46 Quality Assurance 60 sections
- Part 47 Transportation 106 sections
- Part 48 Value Engineering 13 sections
- Part 49 Termination of Contracts 108 sections
- Part 50 Extraordinary Contractual Actions and the Safety Act 34 sections
- Part 51 Use of Government Sources by Contractors 15 sections
- Part 52 Solicitation Provisions and Contract Clauses 680 sections
- Part 53 Forms 61 sections
DFARS (chapter 2, Defense)
- Part 201 Federal Acquisition Regulations System 24 sections
- Part 202 Definitions of Words and Terms 1 sections
- Part 203 Improper Business Practices and Personal Conflicts of Interest 28 sections
- Part 204 Administrative and Information Matters 76 sections
- Part 205 Publicizing Contract Actions 11 sections
- Part 206 Competition Requirements 20 sections
- Part 207 Acquisition Planning 22 sections
- Part 208 Required Sources of Supplies and Services 31 sections
- Part 209 Contractor Qualifications 55 sections
- Part 210 Market Research 2 sections
- Part 211 Describing Agency Needs 22 sections
- Part 212 Acquisition of Commercial Products and Commercial Services 24 sections
- Part 213 Simplified Acquisition Procedures 23 sections
- Part 214 Sealed Bidding 14 sections
- Part 215 Contracting by Negotiation 66 sections
- Part 216 Types of Contracts 36 sections
- Part 217 Special Contracting Methods 64 sections
- Part 218 Emergency Acquisitions 7 sections
- Part 219 Small Business Programs 47 sections
- Part 222 Application of Labor Laws to Government Acquisitions 56 sections
- Part 223 Environment, Sustainable Acquisition, and Material Safety 34 sections
- Part 224 Protection of Privacy and Freedom of Information 2 sections
- Part 225 Foreign Acquisition 251 sections
- Part 226 Other Socioeconomic Programs 14 sections
- Part 227 Patents, Data, and Copyrights 99 sections
- Part 228 Bonds and Insurance 17 sections
- Part 229 Taxes 9 sections
- Part 230 Cost Accounting Standards Administration 2 sections
- Part 231 Contract Cost Principles and Procedures 13 sections
- Part 232 Contract Financing 74 sections
- Part 233 Protests, Disputes, and Appeals 8 sections
- Part 234 Major System Acquisition 13 sections
- Part 235 Research and Development Contracting 16 sections
- Part 236 Construction and Architect-engineer Contracts 25 sections
- Part 237 Service Contracting 67 sections
- Part 239 Acquisition of Information Technology 38 sections
- Part 241 Acquisition of Utility Services 8 sections
- Part 242 Contract Administration and Audit Services 40 sections
- Part 243 Contract Modifications 18 sections
- Part 244 Subcontracting Policies and Procedures 13 sections
- Part 245 Government Property 23 sections
- Part 246 Quality Assurance 39 sections
- Part 247 Transportation 27 sections
- Part 249 Termination of Contracts 14 sections
- Part 250 Extraordinary Contractual Actions and the Safety Act 16 sections
- Part 251 Use of Government Sources by Contractors 5 sections
- Part 252 Solicitation Provisions and Contract Clauses 405 sections
- Part 253 Forms 10 sections
- Part 270 Defense Contracting Programs 7 sections
Source: eCFR, 48 CFR chapters 1 and 2 (GPO GovInfo bulk data) ↗. Rule changes in progress: FAR, DFARS. Terms: glossary.