20 sections with “commencement of work”

  • FAR 22.1014 Delay over 60 days in bid opening or commencement of work.
    If a wage determination was obtained through the e98 process, and bid opening, or commencement of work under a negotiated contract has been delayed, for whatever reason, more than 60 days from the date indicated on the previously submitted …
  • FAR 52.216-23 Execution and Commencement of Work.
    …ted, except that it may be omitted from letter contracts awarded on SF 26: Execution and Commencement of Work (APR 1984) The Contractor shall indicate acceptance of this letter contract by signing three copies of the contract and returnin…
  • FAR 52.211-10 Commencement, Prosecution, and Completion of Work.
    …accommodate the issuance of orders under indefinite-delivery contracts for construction. Commencement, Prosecution, and Completion of Work (APR 1984) The Contractor shall be required to (a) commence work under this contract within __ [Con…
  • FAR 36.213-4 Notice of award.
    …st be promptly executed and returned to the contracting officer; (e) Specify the date of commencement of work, or advise that a notice to proceed will be issued.
  • DFARS 252.222-7003 Permit from Italian Inspectorate of Labor.
    … clause: Permit From Italian Inspectorate of Labor (JUN 1997) Prior to the date set for commencement of work and services under this contract, the Contractor shall obtain the prescribed permit from the Inspectorate of Labor having jurisdi…
  • FAR 52.237-7 Indemnification and Medical Liability Insurance.
    …ill perform under this contract shall be provided to the Contracting Officer prior to the commencement of services under this contract. If the insurance is on a claims-made basis and evidence of an extended reporting endorsement is not prov…
  • FAR 22.1905 Enforcement of Executive Order Minimum Wage Requirements.
    …Department of Labor, shall incorporate the contract clause in the contract retroactive to commencement of performance under the contract through the exercise of any and all authority that may be needed (including, where necessary, its autho…
  • FAR 16.603-4 Contract clauses.
    …racts when a letter contract is contemplated: (1) The clause at 52.216-23, Execution and Commencement of Work, except that this clause may be omitted from letter contracts awarded on SF 26; (2) The clause at 52.216-24, Limitation of Gover…
  • FAR 22.406-1 Policy.
    …hat shall include— (1) Ensuring that contractors and subcontractors are informed, before commencement of work, of their obligations under the labor standards clauses of the contract; (2) Adequate payroll reviews, on-site inspections, and …
  • DFARS 252.228-7006 Compliance with Spanish Laws and Insurance.
    …. (d) The Contractor agrees to represent in writing to the Contracting Officer, prior to commencement of work and not later than 15 days after the date of the Notice to Proceed, that the Contractor has obtained the required types of insura…
  • FAR 11.404 Contract clauses.
    …ate III. (b) Construction. The contracting officer shall insert the clause at 52.211-10, Commencement, Prosecution, and Completion of Work, in solicitations and contracts when a fixed-price construction contract is contemplated. The clause…
  • FAR 12.403 Termination.
    …able Delay” requires contractors notify the contracting officer as soon as possible after commencement of any excusable delay. In most situations, this requirement should eliminate the need for a show cause notice prior to terminating a con…
  • FAR 22.1012-1 Prevailing wage determinations.
    …odification, any revision received by the contracting agency not less than 10 days before commencement of the work shall be effective. (d) If the contracting officer has submitted an e98 to the Department of Labor requesting a prevailing w…
  • FAR 22.1012-2 Wage determinations based on collective bargaining agreements.
    …anged collective bargaining agreement received by the agency not less than 10 days before commencement of the work shall be effective for purposes of the successor contract under 41 U.S.C. 6707(c). (c) The limitations in paragraphs (a) and…
  • FAR 52.212-4 Contract Terms and Conditions—Commercial Products and Commercial Services.
    … notify the Contracting Officer in writing as soon as it is reasonably possible after the commencement of any excusable delay, setting forth the full particulars in connection therewith, shall remedy such occurrence with all reasonable disp…
  • FAR 52.213-4 Terms and Conditions—Simplified Acquisitions (Other Than Commercial Products and Commercial Services).
    … notify the Contracting Officer in writing as soon as it is reasonably possible after the commencement of any excusable delay, setting forth the full particulars in connection therewith, shall remedy such occurrence with all reasonable disp…
  • FAR 52.222-41 Service Contract Labor Standards.
    …yee. The Contracting Officer shall turn over such list to the successor Contractor at the commencement of the succeeding contract. (o) Rulings and Interpretations. Rulings and interpretations of the Service Contract Labor Standards statute…
  • FAR 52.232-12 Advance Payments.
    …ement, or liquidation. (iv) The service of any writ of attachment, levy of execution, or commencement of garnishment proceedings concerning the special account. (v) The commission of an act of bankruptcy. (2) If any of the events describ…
  • FAR 52.245-1 Government Property.
    … the Government upon— (A) Issuance of the property for use in contract performance; (B) Commencement of processing of the property for use in contract performance; or (C) Reimbursement of the cost of the property by the Government, which…
  • DFARS 252.217-7003 Changes.
    …d specifications; (2) Work itemized; (3) Place of performance of the work; (4) Time of commencement or completion of the work; and (5) Any other requirement of the job order. (b) If a change causes an increase or decrease in the cost o…