48 CFR · Federal Acquisition Regulation and Defense supplement

FAR and DFARS navigator

The codified text (eCFR, as of 2026-10-02). Under the Revolutionary FAR Overhaul ↗, agencies follow class deviations with new text for many parts while the formal rules go through the Federal Register: check the solicitation and your contract's clauses, which rule.

Ask the FAR

Try: · · ·

Clear

25 sections with “subcontract settlements”

  • FAR 49.107 Audit of prime contract settlement proposals and subcontract settlements.
    …de a written summary of the review in the termination case file. (b) The TCO shall refer subcontract settlements received for approval or ratification to the appropriate audit agency for review and recommendations when— (1) The amount exc…
  • FAR 49.108-4 Authorization for subcontract settlements without approval or ratification.
    …en request, give written authorization to the prime contractor to conclude settlements of subcontracts terminated in whole or in part without approval or ratification when the amount of settlement (see 49.002(d)) is $100,000 or less, if— (…
  • FAR 49.603-8 Fixed-price contracts—settlements with subcontractors only.
    …Block 14 of SF 30 for settlements of fixed-price contracts covering only settlements with subcontractors.] (a) This agreement settles that portion of the settlement proposal of the Contractor that is based upon termination of the following…
  • FAR 49.108-8 Assignment of rights under subcontracts.
    …ign to the Government, as directed by the TCO, all rights, titles, and interest under any subcontract terminated because of termination of the prime contract. The TCO shall not require the assignment unless it is in the Government's interes…
  • FAR 49.606 Granting subcontract settlement authorization.
    Contracting officers shall use the following format when granting subcontract settlement authorization: LETTER OF AUTHORIZATION (a) Your request of ______ (date) is approved, and you are authorized, subject to the limitations of subsectio…
  • FAR 49.108-7 Government assistance in settling subcontracts.
    … interest to provide assistance to the prime contractor in the settlement of a particular subcontract. In these situations, the Government, the prime contractor, and a subcontractor may enter into an agreement covering the settlement of one…
  • FAR 2.101 Definitions.
    … in the commercial marketplace; and (iii) Offered to the Government, under a contract or subcontract at any tier, without modification, in the same form in which it is sold in the commercial marketplace; and (2) Does not include bulk carg…
  • FAR 15.403-4 Requiring certified cost or pricing data (10 U.S.C. chapter 271 and 41 U.S.C. chapter 35).
    …ontract (except for undefinitized actions such as letter contracts). (ii) The award of a subcontract at any tier, if the contractor and each higher-tier subcontractor were required to furnish certified cost or pricing data (but see waivers…
  • FAR 49.108-3 Settlement procedure.
    (a) Contractors shall settle with subcontractors in general conformity with the policies and principles relating to settlement of prime contracts in this subpart and subparts 49.2 or 49.3. However, the basis and form of the subcontractor's …
  • FAR 49.202 Profit.
    … shall not be allowed (but see 49.108-5). Profit for the contractor's efforts in settling subcontractor proposals shall not be based on the dollar amount of the subcontract settlement agreements but the contractor's efforts will be consider…
  • FAR 49.601-2 Letter notice.
    …tions, it may be used in terminating contracts for other than supplies and in terminating subcontracts. This notice shall be sent by certified mail, return receipt requested, or electronically, provided evidence of receipt is received by th…
  • FAR 49.603-1 Fixed-price contracts—complete termination.
    …een used in arriving at this agreement. (2) The Contractor certifies that each immediate subcontractor, whose settlement proposal is included in the proposal settled by this agreement, has furnished the Contractor a certificate stating (i)…
  • FAR 49.603-2 Fixed-price contracts—partial termination.
    …een used in arriving at this agreement. (3) The Contractor certifies that each immediate subcontractor, whose settlement proposal is included in the proposal settled by this agreement, has furnished the Contractor a certificate stating (i)…
  • FAR 52.249-2 Termination for Convenience of the Government (Fixed-Price).
    …s due under this clause: (1) Stop work as specified in the notice. (2) Place no further subcontracts or orders (referred to as subcontracts in this clause) for materials, services, or facilities, except as necessary to complete the contin…
  • FAR 52.249-3 Termination for Convenience of the Government (Dismantling, Demolition, or Removal of Improvements).
    …s due under this clause: (1) Stop work as specified in the notice. (2) Place no further subcontracts or orders (referred to as subcontracts in this clause) for materials, services, or facilities, except as necessary to complete the contin…
  • FAR 52.249-6 Termination (Cost-Reimbursement).
    …s due under this clause: (1) Stop work as specified in the notice. (2) Place no further subcontracts or orders (referred to as subcontracts in this clause), except as necessary to complete the continued portion of the contract. (3) Termi…
  • DFARS 249.7000 Terminated contracts with Canadian Commercial Corporation.
    … the format prescribed in FAR 49.602 and that they contain the amount of settlements with subcontractors. The termination contracting officer (TCO) shall prepare an appropriate settlement agreement. (See FAR 49.603.) The letter transmitting…
  • FAR 31.205-42 Termination costs.
    … settlement claims to the contracting officer; and (B) The termination and settlement of subcontracts. (ii) Reasonable costs for the storage, transportation, protection, and disposition of property acquired or produced for the contract. …
  • DFARS 252.217-7012 Liability and insurance.
    …erial and equipment due to— (A) Defective workmanship performed by the Contractor or its subcontractors; (B) Defective materials or equipment furnished by the Contractor or its subcontracts; or (C) Workmanship, materials, or equipment wh…
  • FAR 49.002 Applicability.
    …ommercial Services. (b) Contractors shall use this part, unless inappropriate, to settle subcontracts terminated as a result of modification of prime contracts. The contracting officer shall use this part as a guide in evaluating settlemen…
  • FAR 49.206-2 Bases for settlement proposals.
    … costs, initial costs, and general administrative costs; (iii) Costs of settlements with subcontractors; (iv) Settlement expenses; and (v) Other proper charges. (2) An allowance for profit (49.202) or adjustment for loss (49.203(b)) mus…
  • FAR 31.104 Contracts with educational institutions.
    …basis for— (1) Determining reimbursable costs under the contracts and cost-reimbursement subcontracts thereunder performed by educational institutions; (2) Negotiating indirect cost rates; and (3) Settling costs of cost-reimbursement ter…
  • FAR 49.206-1 Submission of settlement proposals.
    …sal. (b) The settlement proposal must cover all cost elements including settlements with subcontractors and any proposed profit. With the consent of the TCO, proposals may be filed in successive steps covering separate portions of the cont…
  • FAR 49.304-3 Submission of vouchers.
    … under the contract. The contractor shall not be reimbursed for costs of settlements with subcontractors unless required approvals or ratifications have been obtained (see 49.108).
  • FAR 52.216-10 Incentive Fee.
    … they are beyond the control and without the fault or negligence of the Contractor or any subcontractor; (ii) The taking effect, after negotiating the target cost, of a statute, court decision, written ruling, or regulation that results in…

FAR (chapter 1)

DFARS (chapter 2, Defense)

Source: eCFR, 48 CFR chapters 1 and 2 (GPO GovInfo bulk data) ↗. Rule changes in progress: FAR, DFARS. Terms: glossary.