48 CFR · Federal Acquisition Regulation and Defense supplement

FAR and DFARS navigator

The codified text (eCFR, as of 2026-10-02). Under the Revolutionary FAR Overhaul ↗, agencies follow class deviations with new text for many parts while the formal rules go through the Federal Register: check the solicitation and your contract's clauses, which rule.

Ask the FAR

Try: · · ·

Clear

7 sections with “terminating the contract for default”

  • FAR 12.403 Termination.
    …lauses prescribed in part 49. Consequently, the requirements of part 49 do not apply when terminating contracts for commercial products or commercial services and contracting officers shall follow the procedures in this section. Contracting…
  • FAR 25.206 Noncompliance.
    …to exercise other contractual rights and remedies, such as reducing the contract price or terminating the contract for default. (4) If the noncompliance is sufficiently serious, consider exercising appropriate contractual remedies, such as…
  • FAR 25.607 Noncompliance.
    …to exercise other contractual rights and remedies, such as reducing the contract price or terminating the contract for default. (4) If the noncompliance is sufficiently serious, consider exercising appropriate contractual remedies, such as…
  • FAR 52.219-11 Special 8(a) Contract Conditions.
    … contracting agency] shall give advance notice to the SBA before it issues a final notice terminating the right of a subcontractor to proceed with further performance, either in whole or in part, under the subcontract for default or for the…
  • FAR 11.501 Policy.
    … contract contains a liquidated damages clause and the contracting officer is considering terminating the contract for default, the contracting officer should seek expeditiously to obtain performance by the contractor or terminate the contr…
  • DFARS 217.7404-3 Definitization schedule.
    …s (e.g., documenting the noncompliance in the contractor's past performance evaluation or terminating the contract for default). (2) Contracting officers shall document in the contract file the justification for withholding or not withhold…
  • FAR 49.607 Delinquency notices.
    …bed to you in the Government's letter of ________ (date)”], the Government is considering terminating the contract under the provisions for default of this contract. Pending a final decision in this matter, it will be necessary to determine…

FAR (chapter 1)

DFARS (chapter 2, Defense)

Source: eCFR, 48 CFR chapters 1 and 2 (GPO GovInfo bulk data) ↗. Rule changes in progress: FAR, DFARS. Terms: glossary.