48 CFR · Federal Acquisition Regulation and Defense supplement

FAR and DFARS navigator

The FAR is the Federal Acquisition Regulation (Title 48, chapter 1 of the Code of Federal Regulations): the rules every federal agency follows when it buys goods and services, from market research and set-asides to contract clauses. It is not the aviation rules (the Federal Aviation Regulations, Title 14). The DFARS is the Defense Department's supplement to it. Every part and section is here, searchable, with a plain-English guide to each part and answers cited to the sections.

The codified text (eCFR, as of 2026-10-29). Under the Revolutionary FAR Overhaul ↗, agencies follow class deviations with new text for many parts while the formal rules go through the Federal Register: check the solicitation and your contract's clauses, which rule. Today's text against the overhaul, side by side.

Ask the FAR

Try: · · ·

Clear

465 sections with “Schedule”: the first 40

  • FAR 8.404 Use of Federal Supply Schedules.
    …)(3) and 19.202-1(e)(1)(iii))do not apply to BPAs or orders placed against Federal Supply Schedules contracts (but see 8.405-5). BPAs and orders placed against a MAS, using the procedures in this subpart, are considered to be issued using f…
  • FAR 45.602-1 Inventory disposal schedules.
    …clearance officers should review and accept, or return for correction, inventory disposal schedules within 10 days following receipt from a contractor. Schedules that are completed in accordance with the instructions for Standard Form 1428 …
  • FAR 52.236-15 Schedules for Construction Contracts.
    As prescribed in 36.515, insert the following clause: Schedules for Construction Contracts (APR 1984) (a) The Contractor shall, within five days after the work commences on the contract or another period of time determined by the Contract…
  • DFARS 245.602-1 Inventory disposal schedules.
    For termination inventory, plant clearance officers shall verify inventory schedules, either directly or through appropriate technical personnel, to determine the following: (a) Allocability. (1) Review contract requirements, delivery sch…
  • FAR 49.206-3 Submission of inventory disposal schedules.
    …ermination inventory is involved, the contractor shall submit complete inventory disposal schedules to the TCO reflecting inventory that is allocable to the terminated portion of the contract. The inventory disposal schedules shall be submi…
  • FAR 49.303-2 Submission of inventory disposal schedules.
    …ermination inventory is involved, the contractor shall submit complete inventory disposal schedules to the TCO reflecting inventory that is allocable to the terminated portion of the contract. The inventory disposal schedules shall be submi…
  • DFARS 208.405 Ordering procedures for Federal Supply Schedules.
    …able source selection process, which are applicable to orders placed under Federal Supply Schedules. (3) See 217.7801 for the prohibition on the use of reverse auctions for personal protective equipment and aviation critical safety items. …
  • DFARS 217.7404-3 Definitization schedule.
    (a) UCAs shall contain definitization schedules that provide for definitization by the earlier of— (1) The date that is 180 days after the contractor submits a qualifying proposal. This date may not be extended beyond an additional 90 days…
  • DFARS 247.271-3 Solicitation provisions, schedule formats, and contract clauses.
    …formance of intra-city or intra-area movement, use the following provisions, clauses, and schedules. Revise solicitation provisions and schedules, as appropriate, if using negotiation rather than sealed bidding. Overseas commands, except th…
  • DFARS 252.236-7008 Contract prices—bidding schedules.
    As prescribed in 236.570(b)(6), use the following provision: Contract Prices—Bidding Schedules (DEC 1991) (a) The Government's payment for the items listed in the Bidding Schedule shall constitute full compensation to the Contractor for— …
  • FAR 14.201-2 Part I—The Schedule.
    The contracting officer shall prepare the Schedule as follows: (a) Section A, Solicitation/contract form. (1) Prepare the invitation for bids on SF 33, or the SF 1447, unless otherwise permitted by this regulation. The SF 33 is the first p…
  • FAR 15.204-2 Part I—The Schedule.
    The contracting officer shall prepare the contract Schedule as follows: (a) Section A, Solicitation/contract form. (1) Optional Form (OF) 308, Solicitation and Offer-Negotiated Acquisition, or Standard Form (SF) 33, Solicitation, Offer and…
  • DFARS 243.204-70-3 Definitization schedule.
    (a) Unpriced change orders shall contain definitization schedules that provide for definitization by the earlier of— (1) The date that is 180 days after issuance of the change order (this date may be extended but may not exceed the date th…
  • FAR 8.405 Ordering procedures for Federal Supply Schedules.
    … establishing a BPA for supplies or services. The procedures in this section apply to all schedules. For establishing BPAs and for orders under BPAs see 8.405-3.
  • FAR 11.402 Factors to consider in establishing schedules.
    (a) Supplies or services. When establishing a contract delivery or performance schedule, consideration shall be given to applicable factors such as the— (1) Urgency of need; (2) Industry practices; (3) Market conditions; (4) Transportat…
  • FAR 18.105 Federal Supply Schedules (FSSs), multi-agency blanket purchase agreements (BPAs), and multi-agency indefinite delivery contracts.
    … procedures and a broad range of goods and services may be available under Federal Supply Schedule contracts (see Subpart 8.4), multi-agency BPAs (see 8.405-3(a)(6)), or multi-agency, indefinite-delivery contracts (see 16.505(a)(8)). These …
  • FAR 36.515 Schedules for construction contracts.
    The contracting officer may insert the clause at 52.236-15, Schedules for Construction Contracts, in solicitations and contracts when a fixed-price construction contract is contemplated, the contract amount is expected to exceed the simplif…
  • FAR 49.602-3 Schedule of accounting information.
    Standard Form 1439, Schedule of Accounting Information, shall be filed in support of a settlement proposal unless the proposal is filed on Standard Form 1438, Settlement Proposal (Short Form) (see 49.206-1(e)).
  • FAR 52.204-28 Federal Acquisition Supply Chain Security Act Orders—Federal Supply Schedules, Governmentwide Acquisition Contracts, and Multi-Agency Contracts.
    …he following clause: Federal Acquisition Supply Chain Security Act Orders—Federal Supply Schedules, Governmentwide Acquisition Contracts, and Multi-Agency Contracts (DEC 2023) (a) Definitions. As used in this clause— Covered article, as …
  • DFARS 208.404 Use of Federal Supply Schedules.
    …lies or services in amounts exceeding the simplified acquisition threshold. (iii) When a schedule lists both foreign and domestic items that will meet the needs of the requiring activity, the ordering office must apply the procedures of pa…
  • FAR 2.101 Definitions.
    …es of these services— (i) Catalog price means a price included in a catalog, price list, schedule, or other form that is regularly maintained by the manufacturer or vendor, is either published or otherwise available for inspection by custo…
  • FAR 4.203 Taxpayer identification information.
    …d the information to the payment office within 7 days of its receipt. (d) Federal Supply Schedule contracts. Each contracting officer that places an order under a Federal Supply Schedule contract (see Subpart 8.4) shall provide the TIN and…
  • FAR 4.1005-1 Required data elements.
    (a) Except as provided in 4.1005-2, each line item or subline item shall include in the schedule (described at 12.303(b)(4), 14.201-2, or 15.204-2, or in a comparable section of the procurement instrument), at a minimum, the following infor…
  • FAR 4.2306 Solicitation provision and contract clauses.
    (a) In all Federal Supply Schedules, Governmentwide acquisition contracts, and multi-agency contracts where FASCSA orders are applied at the order level, the contracting officer shall insert the clause at 52.204-28, Federal Acquisition Supp…
  • FAR 7.105 Contents of written acquisition plans.
    … for compatibility with existing or future systems or programs; and (ii) Any known cost, schedule, and capability or performance constraints. (3) Cost. Set forth the established cost goals for the acquisition and the rationale supporting …
  • FAR 8.401 Definitions.
    …hase agreements (BPA), against the General Services Administration's (GSA) Multiple Award Schedule contracts. A list of eligible ordering activities is available at http://www.gsa.gov/schedules (click “For Customers Ordering from Schedules”…
  • FAR 8.402 General.
    (a) The Federal Supply Schedule program is also known as the GSA Schedules Program or the Multiple Award Schedule Program. The Federal Supply Schedule program is directed and managed by GSA and provides Federal agencies (see 8.004) with a s…
  • FAR 8.403 Applicability.
    …t apply to— (1) Individual orders for supplies or services placed against Federal Supply Schedules contracts; and (2) BPAs established against Federal Supply Schedule contracts. (b) GSA may establish special ordering procedures for a par…
  • FAR 8.405-1 Ordering procedures for supplies, and services not requiring a statement of work.
    … procedures of this subsection when ordering supplies and services that are listed in the schedules contracts at a fixed price for the performance of a specific task, where a statement of work is not required (e.g., installation, maintenanc…
  • FAR 8.405-2 Ordering procedures for services requiring a statement of work.
    …es in this subsection when ordering services priced at hourly rates as established by the schedule contracts. The applicable services will be identified in the Federal Supply Schedule publications and the contractor's pricelists. For establ…
  • FAR 8.405-3 Blanket purchase agreements (BPAs).
    (a) Establishment. (1) Ordering activities may establish BPAs under any schedule contract to fill repetitive needs for supplies or services. Ordering activities shall establish the BPA with the schedule contractor(s) that can provide the su…
  • FAR 8.405-5 Small business.
    …hen setting aside orders and BPAs— (i) Follow the ordering procedures for Federal Supply Schedules at 8.405-1, 8.405-2, and 8.405-3; and (ii) The specific small business program eligibility requirements identified in part 19 apply. (b) O…
  • FAR 8.405-6 Limiting sources.
    Orders placed or BPAs established under Federal Supply Schedules are exempt from the requirements in part 6. However, an ordering activity must justify its action when restricting consideration in accordance with paragraph (a) or (b) of thi…
  • FAR 8.406-2 Inspection and acceptance.
    (a) Supplies. (1) Consignees shall inspect supplies at destination except when— (i) The schedule contract indicates that mandatory source inspection is required by the schedule contracting agency; or (ii) A schedule item is covered by a p…
  • FAR 8.406-4 Termination for cause.
    …may include charging the contractor with excess costs resulting from repurchase. (2) The schedule contracting office shall be notified of all instances where an ordering activity contracting officer has terminated for cause an individual o…
  • FAR 8.406-6 Disputes.
    (a) Disputes pertaining to the performance of orders under a schedule contract. (1) Under the Disputes clause of the schedule contract, the ordering activity contracting officer may— (i) Issue final decisions on disputes arising from perfo…
  • FAR 11.403 Supplies or services.
    (a) The contracting officer may express contract delivery or performance schedules in terms of— (1) Specific calendar dates; (2) Specific periods from the date of the contract; i.e., from the date of award or acceptance by the Government,…
  • FAR 11.404 Contract clauses.
    …he contracting officer may use a time of delivery clause to set forth a required delivery schedule and to allow an offeror to propose an alternative delivery schedule. The clauses and their alternates may be used in solicitations and contra…
  • FAR 16.401 General.
    …ble nor effective to devise predetermined objective incentive targets applicable to cost, schedule, and technical performance; (ii) The likelihood of meeting acquisition objectives will be enhanced by using a contract that effectively moti…
  • FAR 22.404-2 General requirements.
    … the contracting officer must select the most current wage determination(s) from the same schedule(s) as the wage determination(s) incorporated into the contract. (b) If the wage determination is a general wage determination or a project w…

Sections contractors look up most

FAR (chapter 1)

DFARS (chapter 2, Defense)

Understand the FAR fast: which parts to read first, in plain English

Yes: start with the few parts that match what you are doing, read the plain-English guide to each, and ask questions in plain words instead of reading all 3,399 FAR sections. SpendQuery's FAR and DFARS navigator has every part and section, searchable, and Ask the FAR answers from the matching sections and cites each one.

  1. Which FAR. The Federal Acquisition Regulation, the rules for government contracting, is Title 48 of the Code of Federal Regulations. The Federal Aviation Regulations, also called FAR, are Title 14 and aren't here.
  2. The parts a small business meets first. Part 2, Definitions of Words and Terms (3 sections); Part 19, Small Business Programs (126 sections); Part 13, Simplified Acquisition Procedures (49 sections); Part 15, Contracting by Negotiation (81 sections); Part 52, Solicitation Provisions and Contract Clauses (680 sections).
  3. Search, or open a part. Search every section by word at the top of this page, or open a part for its sections and its plain-English guide.
  4. Ask the FAR. Type a question in plain words in the Ask the FAR box above: the answer quotes and links the sections it comes from.
  5. Check deviations and rule changes. This is the codified eCFR text as of 2026-10-29. The FAR is being rewritten (the Revolutionary FAR Overhaul) and agencies apply class deviations before the formal rules are published, so check the note on each part and the FAR rule changes in progress before relying on a section in a contract.
  6. Terms and the official wording. The glossary explains contracting terms; for the final wording, acquisition.gov ↗ and the eCFR are the official sources.

Questions people ask

Is there an easy way to understand FAR rules without reading the whole thing?

Start with the five parts a small business meets first, read each part's plain-English guide, and ask questions in plain words: Ask the FAR answers from the matching sections and cites each one.

  1. Part 2, Definitions: what the terms mean (simplified acquisition threshold, commercial product).
  2. Part 19, Small Business Programs: set-asides, the rule of two, size, 8(a), HUBZone, WOSB and SDVOSB.
  3. Part 13, Simplified Acquisition Procedures: how buys up to the simplified acquisition threshold are made.
  4. Part 15, Contracting by Negotiation: proposals, evaluation, discussions and debriefings.
  5. Part 52, Solicitation Provisions and Contract Clauses: the clauses your contract will contain.

Part 2 → · Part 19 → · Part 13 → · Part 15 → · Part 52 → · Search the FAR, rules and executive orders together → · Guide: the FAR without reading all of it →

Is this the current FAR?

It is the codified text from the eCFR, refreshed monthly. The FAR is being rewritten (the Revolutionary FAR Overhaul): agencies apply class deviations with new text before the formal rules are published, so check the overhaul notice on each part and the rule changes in progress.

FAR rule changes →

Source: eCFR, 48 CFR chapters 1 and 2 (GPO GovInfo bulk data) ↗. Rule changes in progress: FAR, DFARS. Terms: glossary.